Oldfield Primary School, UB6 - Phases 1 and 2

New Build

Oldfield Primary School, UB6 - Phases 1 and 2

The contracts involved the construction of two new buildings to accommodate three classrooms as well as the provision of a link to the existing school.

Form of Contract JCT without quantities 1998 with Amendments 1-4
Contract Value £1.26m Phases 1 & 2
Contract Period 46 weeks combined
Client London Borough of Ealing
Contract Administrator Babcock