Coleridge Primary School, N8

New Build

Coleridge Primary School, N8

The contract comprised the construction of a new performance hall and library, alterations to the connecting access corridor and the installation of disabled access toilet facilities. Works were undertaken during the school term with pupils in occupation.

Form of Contract JCT IFC 1998 with Amendments 1-4
Contract Value £0.367m
Contract Period 29 weeks
Client London Borough of Haringey
Architect and Contract Administrator Curl La Tourelle Architects